What's happening on a Monday...

The sanctuary area has been compacted and tested.  Plumber is laying a water line to the front of the building, and guys are working on the north stage gravel. The Electrician has brought in the wiring to the building.

SAM_0378.JPG
SAM_0376.JPG

Just enough room above the gravel for rebar, concrete and maple hardwood flooring in the sanctuary/gym area.

SAM_0375.JPG

Plumbers are working on laying pipe in the bathroom area.

SAM_0380.JPG